As of October 2026, the first phase of Calgary's Green Line is a roughly 17-kilometre, 11-station line from Shepard in the southeast to a new street-level station on 10 Avenue S in the Beltline. The southeast section has been under construction since 2025 and is targeted to open in 2031; no construction date has been set for the downtown piece, and the north and Seton extensions are not funded. Buy a condo for the transit that exists today, and treat the Green Line as a future bonus.
Where the Green Line stands (October 2026)
| Item | Status |
|---|---|
| Phase 1 route | Shepard (southeast) to a new station on 10 Avenue S near 1–2 Street SW, in the Beltline |
| Length and stations | About 17 km and 11 stations, plus 3 park-and-rides and a maintenance facility at Shepard (City of Calgary, October 13, 2026) |
| Budget | $6.248 billion. Alberta and Canada each contribute $1.53 billion; the City covers the rest and, under the current agreement, any overruns |
| Southeast segment | About 16 km and 10 stations, Shepard to the Event Centre / Grand Central station in Victoria Park. Under construction since June 2025; opening targeted for 2031 |
| Downtown segment | A street-level route along 10 Avenue S, approved by council on September 22, 2026 (12–2). Construction timing not yet set |
| North (Centre Street) and Seton | Not funded. The City is due to report on planning budgets for both, and for a MAX Green bus route to the north, on November 3, 2026 |
Status checked October 26, 2026 against the City of Calgary's Green Line pages and news coverage. Plans for this line have changed several times, so check the City's latest update before relying on a date.
Phase 1 stations and the condo areas they serve
From south to north, the City lists these Phase 1 stations (the exact site of the 10 Avenue station is still to be set):
- Shepard (near 130 Avenue SE; park-and-ride and the maintenance facility)
- Douglas Glen
- Quarry Park
- South Hill
- Ogden
- Lynnwood/Millican
- Highfield
- 26 Avenue SE
- Ramsay/Inglewood
- Event Centre / Grand Central (Victoria Park)
- 10 Avenue S, near 1–2 Street SW (Beltline)
Condo areas it serves: the inner-city end of the line reaches the Beltline along 10 Avenue S, Victoria Park around the new event centre, and Inglewood and Ramsay. Further out, it serves established southeast communities such as Ogden, Millican and Lynnwood, plus Quarry Park and Douglasdale. The Beltline terminus is about a five-minute walk north to the 1 Street SW Red and Blue Line station, where riders transfer to the existing CTrain lines.
For the condo areas closest to stations already running, see our CTrain station map.
How the plan changed, 2017 to 2026
- 2017: Council approved a first stage from 16 Avenue N to Shepard and a long-term 46-km vision from Seton to 160 Avenue N.
- 2020–2021: A revised first phase, with a deep downtown tunnel to Eau Claire, won provincial and federal funding.
- July 30, 2024: To stay on budget, council shortened Phase 1 to run from Eau Claire to Lynnwood/Millican, dropping five southeast stations; the budget rose to $6.248 billion.
- September 2024: The province withdrew its funding over the downtown tunnel, and on September 17 council voted 10–5 to wind the project down.
- December 13, 2024: The province released an AECOM-led alternative: Shepard to Victoria Park, then elevated through downtown on 10 Avenue S and 2 Street SW.
- January 28, 2025: Council accepted the provincial plan, started the southeast segment and ordered a study of the elevated downtown route. Ottawa approved the revised business case in March 2025, and construction began at Shepard in June 2025.
- September 2026: After the elevated options came in hundreds of millions to about $1 billion over budget, a committee (September 8) and then council (September 22) chose a street-level route on 10 Avenue S instead. The surface route has the lowest ridership forecast of the three options, about 41,000 trips a day.
- October 13, 2026: The City awarded the contract for the Bow River package — the Ogden Road, Bow River and Deerfoot Trail bridges.
What the Green Line won't serve (for now)
- The downtown core, East Village, Chinatown and Eau Claire get no Green Line station in Phase 1. The line ends in the Beltline, short of 7 Avenue.
- The north — Centre Street N and 16 Avenue N to 160 Avenue N — has no construction funding.
- Seton and the far southeast beyond Shepard have no construction funding.
The City says further work will proceed as funding becomes available. A report on planning budgets for the north and south extensions is due at Executive Committee on November 3, 2026.
What it means for condo buyers
- Price in today's transit. The southeast stations are targeted for 2031, and the downtown station has no construction date. Value a condo on the transit, walkability and amenities it has now.
- Expect construction. Building the guideways, bridges and stations means road changes and noise near the line for several years. The City publishes where work is happening each year.
- Area plans are unsettled. The City's station-area plans for Millican-Ogden and Inglewood-Ramsay were drafted for the old route and have been paused or folded into broader local area plans, so zoning around future stations may still change.
- Check the distance yourself. Walking distance to a future station only helps if the station opens where it's planned. Ask us to map a building against the latest station sites.
Quick Answers
When will Calgary's Green Line open?
Where will the Green Line go?
Does the Green Line go downtown?
How much does the Green Line cost?
Is the Green Line still being built?
Sources: City of Calgary — About Green Line · City of Calgary — Green Line stations · City of Calgary — Green Line downtown segment · City of Calgary — It's official: the downtown segment is approved (Sept 22, 2026) · City of Calgary — Bow River infrastructure contract (Oct 13, 2026) · City of Calgary — Where you'll see Green Line construction in 2026 · City of Calgary — Transit-oriented development · Global News — Green Line surface route finalized (Sept 23, 2026) · Global News — Committee endorses downtown route (Sept 8, 2026) · CBC News — Council confirms downtown Green Line route (Sept 22, 2026) · CTV News — Green Line to run down 10 Avenue (Sept 22, 2026) · LiveWire Calgary — Committee approves surface path (Sept 8, 2026) · LiveWire Calgary — Green Line cut down in south Calgary (July 30, 2024) · Global News — Council votes to wind down Green Line (Sept 18, 2024) · LiveWire Calgary — Province delivers new Green Line plan (Dec 13, 2024) · Global News — Council approves new Green Line plan (Jan 29, 2025) · CTV News — Green Line back on track after federal approval (Mar 18, 2025)
General information for Alberta condo buyers, not legal, tax or financial advice. Confirm details with your REALTOR®, lawyer, lender or accountant.

Elevate Realty Group
We're an Alberta real estate team with Real Broker, helping condo buyers and sellers across Calgary's Beltline, Downtown, East Village, Mission and beyond. We know what to look for in condo documents, reserve funds and bylaws, and we give you straight answers — no pressure.
- Market knowledge — neighbourhoods, building types and recent sales across Calgary
- Condo document review — once your offer is accepted, we flag red flags before you waive conditions
- Buyer, seller and investor experience — first condos, downsizes and rental portfolios
Live Condo MLS® Listings
Search every condo on the Calgary MLS®, updated daily — then let a local condo specialist help you separate the great buildings from the money pits.